Mastec-built Virginia to W.Va. natural gas project, set to operate in summer, faces unclear delay as feds must reassess its water crossings in a national forest.
Federal judge allows construction for now on $492M Wisconsin-to-Iowa line in opponent challenge, but chides utilities and agencies over Mississippi River crossing permit flaws. Project, set to carry western renewable energy to markets, has support from one Wisconsin non-profit.
Agency said it will deny three utility extensions for unlined pond compliance over groundwater pollution risks, as part of larger agency push to strengthen regulation of power plant residuals disposal and facilities with improper storage.
Work near Edson on the $10B Trans Mountain oil pipeline expansion, $1.8B expanded NGTL gas line and $1.2B Cascade Energy power plant has brought at least 2,500 workers to town, with housing scarce.