Johnson Bros. Corp. says Charlotte caused delays and provided inadequate plans, while the city counters that it's owed millions from the Texas-based contractor it says failed to complete punch list items and performed "poor work."
Protracted work on already late rail link could stretch project completion seven months beyond a fall 2026 target for its new design-build team and for just named state Transportation Secretary Paul Wiedefeld, a sector veteran.
No doubt the New York Metropolitan Transportation Council has its reasons, but the planning group’s list of projects; for which it seeks $15 billion in federal funding support over the next five years, includes the LaGuardia Airport AirTrain.
The Southwest Light Rail green line extension was designed to connect downtown Minneapolis with suburban communities of Eden Prairie, Hopkins, Minnetonka and St. Louis Park.
An
extension of the Southwest Light Rail Transit in Minnesota is nine
years behind schedule and $1.5 billion over budget, according to a
recently released report by
a state auditor.