Federal Review
NCPC Tables White House Ballroom Vote as Federal Filings Detail Rebuild Case
Federal planning commission delays decision until April after lengthy public testimony

Rendering shows the proposed White House State Ballroom extending east of the executive residence as part of the East Wing modernization project. The roughly 22,000-sq-ft event space is designed to seat about 1,000 guests.
Federal planners reviewing the White House East Wing modernization proposal delayed a decision on President Donald Trump’s new ballroom until April after nearly two hours of public testimony at a March 5 meeting of the National Capital Planning Commission.
Staff recommended approving the final site and building plans, arguing that the public will see little change to the White House’s primary views because pedestrian sight lines will mostly be blocked by existing landscaping. However, commissioners decided to postpone the decision until their April meeting after hearing lengthy testimony from preservation groups, architects and private citizens.
The project’s program is not modest. Staff describes a roughly 22,000-sq-ft ballroom designed for about 1,000 guests, within about 89,000 sq ft across two above-ground visible floors, along with support facilities, including a commercial kitchen, a First Lady office suite and a replacement movie theater.
The delay lands against two pressures surrounding the proposal: a public-comment record exceeding 30,000 submissions—most opposing the project—and an active federal lawsuit. U.S. District Court Judge Richard J. Leon recently denied the National Trust for Historic Preservation’s request for a preliminary injunction but indicated the dispute could return quickly if plaintiffs reframe their challenge to directly question presidential statutory authority.
The design has already cleared one federal design review hurdle. The U.S. Commission of Fine Arts approved the concept and final plans at its Feb. 19 meeting.
Construction Intelligence in the Federal Record
The submission identifies Shalom Baranes Associates Architects as the project architect and includes detailed engineering and construction documentation that rarely appears in early-stage federal planning filings.
In a Feb. 5 memorandum submitted to the commission, Joshua Fisher, assistant to the president and director of the White House Office of Administration, lays out the administration engineering case for a full rebuild rather than a retrofit.
Looking for quick answers on construction and engineering topics?
Try Ask ENR, our new smart AI search tool.
Ask ENR →
Architectural elevation drawings submitted to the National Capital Planning Commission for the White House East Wing modernization show the proposed State Ballroom facade, including a revised portico design that removes the triangular pediment.
Rendering courtesy of NCPC
The White House asserts that bringing the former East Wing and colonnade up to modern security and structural requirements would have required stripping the buildings “to the shell and structural walls,” then inserting additional structural support throughout in ways that would permanently alter layouts and finishes.
Fisher ties the reconstruction decision to specific condition issues, citing chronic water intrusion and substructure leaks, mold contamination and life-safety deficiencies, including egress and compartmentation issues that, he wrote, created an “unacceptable risk to occupants.”
It is the most direct articulation in the federal planning file to date of why the project team argues the existing East Wing could not be modernized in place without fundamental structural intervention.
Commission staff also noted the design has evolved since the Jan. 8 information presentation. Among the changes was removal of a triangular pediment on the south facade, which staff said lowers the perceived height and simplifies the roofline.
RELATED
US Commission of Fine Arts Approves Trump Ballroom Design, Next Stop is NCPC Vote
Even with approval recommended, staff flagged one remaining design pressure point, saying the south portico’s dense column spacing could create what the report described as a “heavy, dark facade” and urging further refinement.
The same submission describes a protection plan in jobsite terms: heavy equipment kept “at a safe distance” from the Executive Mansion, selective hand removal nearest the mansion, stabilization to prevent collapse and vibration and crack-movement monitoring to confirm that ongoing work does not harm the mansion or nearby structures. ENR has previously reported on the project’s constrained staging and monitoring regime.
Submission Materials
NCPC | East Wing Modernization Project
The National Environmental Policy Act (NEPA) record now includes a key interface detail that engineers and general contractors will note immediately: limited portions of the Executive Mansion’s previously removed east facade will be reinstalled to align the two levels. The NEPA decision file also pins down the staging footprint and duration.
It describes a temporary construction zone through summer 2028 that would close Madison Place NW between H Street NW and E Street NW and restrict portions of Pennsylvania Avenue, extending about 260 ft east and 350 ft west from Madison Place’s centerline.
The filing anticipates heavy-lift logistics. ENR previously reported that a crane and other heavy equipment have been staged on site in anticipation of the federal review process advancing.
Baranes, the project architect, defended the ballroom’s size during the meeting, telling commissioners the massive floor plate reflects security and operational requirements unique to presidential events. The space must accommodate not only 1,000 seated guests but also camera platforms, security circulation aisles, staging areas and ceremonial elements such as military color guards.
“Those events require layers of circulation and security that simply don’t exist in a typical hotel ballroom,” Baranes told commissioners.
The NEPA file also describes selective salvage landscape work not previously reported, including the removal of commemorative Southern Magnolia trees due to the new footprint, careful removal and reinstallation of the East Garden, storage and relaying of brick pavers, dismantling and preserving of the fountain and statue for reinstallation, and rigid-barrier protection for the Laura Bush Silver Linden Tree during construction.
“Our intent is to protect and reinstall as much of the existing landscape fabric as possible,” said Rick Parisi, principal at MPFP and the project's landscape architect, describing the plan to carefully remove and store garden elements before construction and restore them once the new structure is complete.
The submission sheets highlight coordination complexity by listing specialist consultants such as food service, acoustic and vibration, AV and vertical transportation.
On the civil side, the grading plan notes an existing rectangular granite drainage channel along the security fence will remain and be integrated into the new storm drain system, with existing trench drains at two gates kept functional during construction.
RELATED
Watchdog Sues for Records on White House Ballroom Project
Preservation Groups Press Case During Testimony
The commission entered the meeting with a heavily lopsided public-comment record. Staff reported more than 30,000 submissions as of the report date, with the vast majority opposing the project.
Architectural plans and elevation drawings submitted with federal review filings show the footprint and massing of the proposed White House East Wing modernization and State Ballroom addition, including the above-grade event space and below-grade support areas.
Credit: AP Photo/Jon Elswick
Carol Quillen, president and CEO of the National Trust for Historic Preservation—the plaintiff in the still-open lawsuit—opened the public testimony by urging commissioners to slow the process and consider alternatives.
“You don’t have to choose between respecting our history for the American people and accommodating modern government’s needs,” she said, arguing that a smaller and lower ballroom could still host large events while preserving historic sight lines and the architectural primacy of the White House.
Several speakers focused on architectural scale. David Scott Parker, a Rhode Island architect and Fellow of the American Institute of Architects, told commissioners the ballroom portico alone would be “166% larger than the White House South Portico” and argued the proposal exceeds typical ballroom sizing standards.
Staff also reiterated that many objections fall outside the commission's statutory jurisdiction, including concerns about demolition already completed and the project’s funding structure. The ballroom proposal has been described by the administration as privately funded through donations rather than by congressional appropriations, an issue commissioners said is not within the planning body’s authority to evaluate.
Public testimony stretched nearly two hours—longer than the procedural portion of the meeting itself—as preservation groups, architects and private citizens criticized the ballroom’s scale and its potential effect on the historic White House campus.
RELATED
Private Funding May Deliver Trump’s White House Ballroom—but What Pays for the Rest?
What Happens Next
Rather than voting on the proposal, commissioners tabled the decision until their April meeting after hearing the extended testimony, saying that additional time would allow them to review the unusually large public record associated with the project.
Commission Chair William Scharf, who also serves as Trump White House staff secretary, said the April meeting will focus on commissioner deliberations before a final vote on the staff recommendation.
Staff said the commission’s eventual action would also trigger adoption of the Environmental Assessment prepared by the National Park Service for commission use, allowing a Finding of No Significant Impact (FONSI) under NEPA to be signed.
Beyond the ballroom decision itself, staff used the record to signal additional filings likely ahead. The administration plans to submit individual security projects—both temporary and permanent—across the White House complex and nearby areas, indicating further commission reviews could follow.
Whether the ballroom ultimately rises now hinges on the commission’s April vote—and on the still-active federal lawsuit challenging the project.



