This website requires certain cookies to work and uses other cookies to help you have the best experience. By visiting this website, certain cookies have already been set, which you may delete and block. By closing this message or continuing to use our site, you agree to the use of cookies. Visit our updated privacy and cookie policy to learn more.
This Website Uses Cookies By closing this message or continuing to use our site, you agree to our cookie policy. Learn MoreThis website requires certain cookies to work and uses other cookies to help you have the best experience. By visiting this website, certain cookies have already been set, which you may delete and block. By closing this message or continuing to use our site, you agree to the use of cookies. Visit our updated privacy and cookie policy to learn more.
In the days before a large fire closed Pittsburgh’s Liberty Bridge for 24 days in September, crews working on the $80-million bridge rehabilitation squelched two minor fires, according to Occupational Safety and Health Administration documents obtained by the Pittsburgh Post-Gazette under the Freedom of Information Act.
Despite a fire on Pittsburgh’s Liberty Bridge last month, contractor Joseph B. Fay Co. missed by only four days a milestone to open the bridge’s fourth lane to traffic.
The fire damage to Pittsburgh’s Liberty Bridge took longer than expected to repair, but the bridge that connects the Steel City’s downtown to the Liberty Tunnels finally reopened to traffic on Monday afternoon.
The Pennsylvania Dept. of Transportation announced Friday afternoon that Pittsburgh’s fire-damaged Liberty Bridge will remain closed indefinitely as crews continue to repair 30 feet of a compression chord on a deck truss that was damaged in a Sept. 2 blaze. PennDOT, which hoped to finish the work by Monday, did not specify when the work would be done.