Skanska and FlatironDragados are advancing a $445M roadway package at LAX, reconfiguring access and bridges while coordinating construction amid multiple overlapping airport megaprojects.
Los Angeles International Airport modernization includes a new terminal with 12 to 18 new gates as well as development of Concourse 0 with six to nine net new gates and airfield upgrades.
Executives discussed building big with limited resources at the Western Winter Workshop infrastructure project delivery event in California earlier this month.
The $344-million, five-story connection between Terminals 1 and 2 provides nearly 240,000 sq ft for ticket counters, baggage carousels, a bus gate and an additional screening checkpoint as well as a vertical circulation core that will connect with LAX’s future automated people mover.