Tight footprints, tight timelines and tight regulations at the University of California – Davis Health medical building led to a Boldt Co. partnership with Mark III Construction that moved construction manufacturing offsite to complete the $5 million project in a seven-month window.
The project team found success not only by embracing prefabrication but also through collaboration and coordination – which led to manufacturing the new structure at Mark III’s 24,000-sq-ft California prefabrication facility about 22 miles away before assembling the walls over two days at the school’s on-campus Sacramento site.