Construction started on the U.K.’s London–Birmingham high speed railroad only last month, and already project costs have risen by more than $1 billion. Additional pandemic-related costs will be disclosed next spring.
The discovery of greater than expected asbestos and other snags in preparatory work are expected to add $520 million to the project’s cost. A similar hike is forecast for work at the main London terminal at Euston.