Owner/Developer and Construction Manager Related Cos. Lead Design Firm Office for Metropolitan Architecture General Contractor Webcor Civil/Structural Engineer MKA Concrete Webcor Concrete
A concrete pour cycle that took just three days per floor is the highlight of the Transbay Block 8 project in San Francisco. It was a key factor in enabling the team to finish the $300-million project, which includes a high-rise residential building, in May 2018, only about 14 months after its groundbreaking.