The partial shutdown of the federal government is starting to affect some federal construction programs—such as those at the Federal Transit Administration—but other major infrastructure accounts have full 2019 funding and aren't harmed.
Freight and commuter railroads across the U.S. achieved enough milestones by a Dec. 31, 2018, federal deadline for installing automatic train control systems to avoid potential federal penalties.
I once attended training for fleet drivers who frequently tow trailers. During discussion of attaching the trailer hitch to the truck, the instructor asked if the operators crossed the safety chains under the tongue when connecting.
Federal auditors say U.S. Energy Dept. PM inexperience led to the estimated final cost of the Mixed Oxide Fuel facility in South Carolina rising to $17.2 billion from its original $4.8-billion estimate, and its planned finish pushed out 32 years.