Best of the Best Winners
How Sanibel Turned Disaster into an Infrastructure Blueprint
.webp?t=1773961394)
With the only road connecting Sanibel and Captiva severed by Hurricane Ian, rebuilding the Sanibel Causeway was one of Florida’s most challenging infrastructure projects in decades.
Hurricane Ian Sanibel Access Project
Sanibel, Fla.
Project of the Year Finalist and Highway/Bridge
Submitted by: Superior-de Moya Joint Venture
Region: Texas & Southeast
Owner: Florida Dept. of Transportation
Lead Design Firm/Civil Engineer: Kisinger Campo & Association
General Contractor: Superior-de Moya
Structural Engineer: H&H (Hardesty & Hanover)
High winds, storm surge and a collapsing coastal corridor made the reconstruction of the Sanibel Causeway one of Florida’s most demanding infrastructure efforts in decades. With the only road connecting Sanibel and Captiva severed by Hurricane Ian, the team mobilized quickly and executed with precision, applying targeted design adjustments and a delivery model built for speed to rebuild a 75-year-old corridor that has since held firm through multiple storms.
The causeway is the only access route for residents, workers, emergency responders and millions of visitors each year. When Ian made landfall on Sept. 28, 2022, the Category 4 storm washed out approaches and embankments, isolating more than 6,400 residents. The Florida Dept. of Transportation issued an emergency contract assigning Superior Construction, in partnership with Ajax Paving, to stabilize the corridor and restore temporary access. Despite washed-out roads, limited staging areas and widespread power outages, crews worked around the clock and reopened the route in 15 days—two weeks ahead of schedule.
Crews work to rebuild the Sanibel Causeway following Hurricane Ian’s destruction in 2022.
Photo courtesy of Superior Construction
The emergency work, however, revealed deeper vulnerabilities. The original 1963‑era design relied on mechanically stabilized earth (MSE) walls and embankments that could not withstand sustained hydrostatic pressure and wave action. A full rebuild was necessary, prompting FDOT to shift the corridor into phased design‑build—its first use of the method for a catastrophic event. The permanent reconstruction was awarded to the Superior–de Moya joint venture, combining Superior’s heavy civil and marine capabilities with the de Moya Group’s coastal and structural expertise. Work began in September 2023, backed by $51.6 million in state funding approved earlier that year.
Superior Construction Area Manager Toby Mazzoni says two early decisions proved pivotal. The first was treating emergency repairs as permanent infrastructure from day one, eliminating the need to remove temporary structures later. The second was shifting from traditional MSE walls to a steel sheet-pile system with king pile technology. “The steel sheet pile system wasn’t just substituted for the MSE walls,” he says, adding it was deployed to harden the roadway and protect bridge substructures and approaches, a scope informed by the use of ADvanced CIRCulation and Simulating Waves Nearshore coastal modeling.
Photo courtesy of Superior Construction
Permanent reconstruction reached substantial completion in 105 days, meaning the full structural rebuild was finished, and the corridor was ready for traffic. Crews installed 750,000 sq ft of steel sheet pile, raised seawalls to 8 ft from 5 ft, rebuilt embankments, added underdrains and armored shorelines with 127,996 tons of stone. The roadway elevation was increased to improve storm‑surge performance, and advanced drainage systems were installed to reduce long‑term maintenance needs.
The work required careful coordination with weather, tides and marine traffic. Crews operated from barges and temporary platforms in shifting wind conditions, sequencing operations to maintain access while advancing sheet‑pile installation, shoreline armoring and roadway reconstruction. The phased design‑build approach enabled FDOT and the contractor to issue advance work packages and refine design elements as construction moved forward.
The 2024 hurricane season became the project’s first major proving ground. Completed sections withstood the direct impacts of Hurricanes Debby, Helene and Milton with minimal damage, affirming the modeling-driven decision to shift from traditional MSE walls. While unfinished areas saw washouts, the hardened features performed as intended. “During those three hurricanes, the steel sheet pile wall systems, elevated roadway profile and marine mattress scour protection all performed as intended—a real-world confirmation of the design team’s decisions,” Mazzoni says.
Looking for quick answers on construction and engineering topics?
Try Ask ENR, our new smart AI search tool.
Ask ENR →
Photo courtesy of Superior Construction
The project also delivered ecological and community gains. In 2025, the Sanibel‑Captiva Conservation Foundation recorded the most successful nesting season for least tern seabirds on the causeway islands since the 1990s, marking the third year of a steady rebound. Black skimmer seabirds also returned, as did economic activity, with causeway traffic reaching 82% of pre‑Ian levels and overall business recovery hitting 74% by late 2025.
“This corridor is built to handle what’s coming,” Mazzoni says. “The systems we put in place are doing exactly what they were designed to do, and they’ll keep protecting this link for years to come.”



