Submitted by Mountain Crane Service

This project consisted of a three-week shutdown of a portion of a refinery in Salt Lake City to move live stacks and add equipment, perform repairs and complete improvements. Crane operators and safety foremen worked to complete the job on time by running a three-week schedule 24/7. The project was completed on time, within budget, and the refinery was able to keep running during the streamlined project.

Alky Turnaround (Chevron Refinery Shutdown)
Alky Turnaround (Chevron Refinery Shutdown)
Project Team: Salt Lake City

Owner: Chevron
Contractor: Chevron/Harder Mechanical
Among the Subcontractors: Mountain Crane Service
Start: April 6, 2009
Finish: April 30, 2009