Submitted by Mountain Crane Service
This project consisted of a three-week shutdown of a portion of a refinery in Salt Lake City to move live stacks and add equipment, perform repairs and complete improvements. Crane operators and safety foremen worked to complete the job on time by running a three-week schedule 24/7. The project was completed on time, within budget, and the refinery was able to keep running during the streamlined project.


Project Team: Salt Lake City
Owner: Chevron
Contractor: Chevron/Harder Mechanical
Among the Subcontractors: Mountain Crane Service
Start: April 6, 2009
Finish: April 30, 2009
Owner: Chevron
Contractor: Chevron/Harder Mechanical
Among the Subcontractors: Mountain Crane Service
Start: April 6, 2009
Finish: April 30, 2009
Post a comment to this article
Report Abusive Comment