2025 West Best Projects
Best Airport/Transit: Alaska Airlines LAX Terminal 6 Redevelopment Project

Alaska Airlines LAX Terminal 6 Redevelopment Project
Los Angeles
BEST PROJECT
Submitted by PCL Construction
Owner Alaska Airlines
Lead Design Firm Rivers & Christian
General Contractor PCL Construction
Civil Engineer Burns & McDonnell
Structural Engineer KPFF Consulting Engineers
MEP Engineer PBS
Electrical/ Low Voltage Gurcinas & Associates
Airside/PBB Aero Systems
This three-year redevelopment project modernized a 1960s-era terminal and expanded its gate capacity, all without disrupting daily airport operations. Scope of work included about 100,000 sq ft of improvements to the terminal, airside and utilities. The terminal’s capacity went to 15 gates from 13, and the team built a 25,000-sq-ft expansion of boarding areas and renovated 12 gates.
Airside upgrades were made as well, including more than 70,000 sq ft of new aircraft-rated concrete paving, a reconfigured apron layout and drainage, relocated jet bridges and fuel hydrants and a new jet fuel main serving all 15 gates. To tie into LAX’s live 12-in. jet fuel main, the team replaced traditional welding with a PLIDCO mechanical fitting, which reduced fuel line downtime to four hours from 12, eliminated extended tanker truck support and significantly reduced fire risk.
Photo by Paul Turang Photography
Underground infrastructure was also overhauled, with new electrical, communications, water, sewer, storm drainage and fire protection systems. The team discovered that a live 8-in. fire water main was running through 21 planned caisson locations for the new terminal expansion. This existing line provided fire protection to half the terminal and was not shown in early design documents. The contractor developed a phased mitigation plan that involved constructing a new riser manifold, performing two cut-and-cap operations and rerouting several 4-in. sprinkler mains, including one directly above an active baggage claim. All work on the fire water main went through sequencing with the Los Angeles Dept. of Building and Safety, the fire marshal, Los Angeles World Airports and Alaska Airlines to ensure uninterrupted fire protection.
Two new structural steel and concrete building additions expanded the facility’s total footprint to more than 96,000 sq ft. Phased delivery, temporary barricades and precise coordination with LAWA and Alaska Airlines ensured uninterrupted operations throughout.
Terminal 6 also has the first half-bay moment frame ever approved by the city of Los Angeles, allowing demolition and structural upgrades within an occupied terminal and without compromising structural integrity.


