SPRINGFIELD, PA—J. J. DeLuca of Springfield, Pa. started four new projects this fall. Site development is in progress for the new Weschler Building @ Elwyn in Media, Pa. The $9 million, 40,000-sq-ft project is expected to complete in spring 2010. The architect is RHJ Associates of King of Prussia, Pa.

Demolition of the Mosteller Garage in West Chester Borough, Pa is complete and will soon be the home of a new seven-story parking garage containing 689 parking spaces. The $12 million job is scheduled to complete in fall 2010.

The Connelly House, located in downtown Philadelphia, will be an eight-story mixed-use project for Project H.O.M.E, Bethesda Project and the Archdiocese of Philadelphia. The project plans to open in November 2010.

Ground was recently broken on a 24-acre site for the new Ambler Area YMCA in Lower Gywnedd Township, Pa. The 80,000-sq-ft, $15 million facility was designed by Kramer Marks and is anticipated to complete Fall 2010.