2025 East Best Projects
Best Specialty Construction: E-Commerce Warehouse Bar Joist Reinforcement Project

E-Commerce Warehouse Bar Joist Reinforcement Project
Jessup, Pa.
BEST PROJECT
Submitted by JGM Fabricators & Constructors
Owner: NorthPoint Development
Lead Design Firm: DCI
General Contractor: JGM Fabricators & Constructors
Unable to handle area snow loads, the undersized roof structure on a 750,000-sq-ft warehouse required reinforcement of 2,300 bar joists and more than 200 girders, all without disrupting the floor operations of a nationally recognized, online e-commerce distribution center.
Tackling this challenge required the strategic erection of more than 60,000 sq ft of hanging scaffolding, which was moved 11 times to meet the evolving needs of the build. A multidisciplinary crew of certified welders, fitters, operators, carpenters, laborers and safety professionals was mobilized to ensure seamless execution. The team installed more than 187,000 linear feet of weld and utilized eight custom-engineered girder jacking systems, completing the project on schedule and at budget.
Photo courtesy JGM
Because some of the girders could not be jacked up from the floor using shoring towers, the team custom-engineered an innovative roof-based jacking system that would lift the girders from outside. Placing a cribbing stand atop the column locations, the team spanned the girder with two jacking beams. Cable was run through the roof and coupled to the bottom of the girder. Using a hydraulic jack on the beams, the team was able to “unload” the girders before the reinforcing steel was welded on. Strain gauges were utilized to remotely monitor the roof structure, ensuring that the loads introduced from the scaffolding, reinforcement operations and snow loads during the winter months did not exceed the structure’s capacity.
During the project, the team conducted more than 530 formal safety inspections, resulting in zero lost-time incidents and no disruption to the sensitive operations taking place beneath the work area. Because the scaffold deck blocked the sprinkler system, fire watch personnel were positioned both above and below the deck throughout the project. To safeguard air quality during extensive welding activities, the team deployed real-time environmental monitoring coupled with the temporary installation of high-capacity exhaust fans to manage smoke from welding operations. Safety netting protected workers, equipment and inventory prior to moving the scaffolding.


