COVID, supply limitations and budget overruns forced Chemex Global’s team to be resilient and proactive to mitigate impacts during the construction of the Encina Pilot Plant. During construction, new technologies were developed, including specialized valve packing material, heat-resistant electrical tracing and increased process monitoring. Also, the project team was able to offset costs by providing engineering and material recommendations.
During the first week, an error was discovered in the materials balance calculations provided in the original design package. This error needed to be rectified before equipment procurement and design could proceed. The engineering team addressed the issue with minimal schedule delay.