Facing a stringent deadline to be ready for the first Utes football game of the 2021 season, the project team building this 6,000-seat addition to the stadium had to effectively manage a broad range of stakeholders to keep the project on track.
To ensure the project was on time and budget, OAC meetings were held whenever a new product was incorporated. Crews installed a small portion at a time, and the entire OAC team then reviewed it to identify solutions to any potential problems. This helped keep trade partners on schedule and ensured availability of any additional resources.