This website requires certain cookies to work and uses other cookies to help you have the best experience. By visiting this website, certain cookies have already been set, which you may delete and block. By closing this message or continuing to use our site, you agree to the use of cookies. Visit our updated privacy and cookie policy to learn more.
This Website Uses Cookies
By closing this message or continuing to use our site, you agree to our cookie policy. Learn More
This website requires certain cookies to work and uses other cookies to help you have the best experience. By visiting this website, certain cookies have already been set, which you may delete and block. By closing this message or continuing to use our site, you agree to the use of cookies. Visit our updated privacy and cookie policy to learn more.
Subscribe
  • Sign In
  • Create Account
  • Sign Out
  • My Account
  • Midwest
  • News
    • Newswire
  • Features
    • Projects
    • Companies
  • Top Lists
  • Current Issue
  • Blogs
  • Submit Your Photos
    • People
    • Projects
    • Events
  • Resources
    • Proposal & Bids
    • Industry Jobs
    • Subscribe
    • eNewsletter
    • Events
    • Advertise
    • Reprints and Plaques
    • Staff Directory
    • Construction Cities
  • ENR Home
  • Other Regions
    • ENR Home
    • California
    • MidAtlantic
    • Midwest
    • Mountain States
    • New York
    • New England
    • Northwest
    • Southeast
    • Southwest
    • Texas & Louisiana
Home » Best Project – Residential/Hospitality: University of Chicago Campus North Residential Commons
2017Midwest Construction ProjectsMidwestFeaturesBest Projects
ENR Midwest’s 2017 Best Projects

Best Project – Residential/Hospitality: University of Chicago Campus North Residential Commons

University of Chicago Campus North Residential Commons

In developing its new Campus North Residential Commons project, the University of Chicago saw an opportunity to complete and open facilities a year early by using a design-build delivery method versus its traditional design-bid-build approach.

PHOTO: TOM HARRIS PHOTOGRAPHY/MORTENSON CONSTRUCTION

University of Chicago Campus North Residential Commons

In developing its new Campus North Residential Commons project, the University of Chicago saw an opportunity to complete and open facilities a year early by using a design-build delivery method versus its traditional design-bid-build approach.

PHOTO: TOM HARRIS PHOTOGRAPHY/MORTENSON CONSTRUCTION

University of Chicago Campus North Residential Commons
University of Chicago Campus North Residential Commons
November 14, 2017
KEYWORDS ENR Midwest Best Projects
Reprints
No Comments

University of Chicago Campus North Residential Commons
Chicago               
Best Project

Owner: University of Chicago
General Contractor: Mortenson Construction
Lead Design Firm: Studio Gang Architects
Structural Engineer: Magnusson Klemencic Associates
MEP Engineer: dbHMS


In developing its new Campus North Residential Commons project, the University of Chicago saw an opportunity to complete and open facilities a year early by using a design-build delivery method versus its traditional design-bid-build approach. The project marked the university’s first major design-build effort and opened in September 2016.

Designed by Studio Gang Architects, the housing complex allows students of all academic years to live and work together with the goals of elevating social and academic success. The 400,000-sq-ft residence hall is spread among four separate but interconnected buildings, ranging from one to 15 stories. The buildings are interconnected by plazas, gardens, walkways and courtyards.

The 15-story, 11 story and five-story buildings contain a combined eight “houses,” accommodating a total of 800 undergraduate students. Each house includes a three-story common area—called a hub—where students can gather, study and relax. The top floor reading room offers panoramic views of the Chicago skyline and Lake Michigan.

The one-story dining center overlooks a central quadrangle. Offices for campus and student life, classrooms, music practice rooms, outdoor green spaces and 10,000 sq ft of ground-level retail space are also provided.

Since large-scale design-build was a new process to the university, the team focused on meticulously creating and following a detailed schedule, which proved to be the most demanding aspect of the project, says Carl Kreiter, senior project manager at Mortenson Construction. The structural, enclosure and MEP systems were incorporated into a building information model, enabling the team to include the schedule and create a 4D model.

“Using that as a communication tool to our subcontractors and university stakeholders was extremely valuable, especially on a site that included separate building that are all interconnected,” he says.

The team also created a two-story mock-up, which aided the entire project team in design evaluation and constructibility. Some precast detailing was modified, waterproofing details were incorporated at the foundation transition and a method of prefabricating radiant tubing was developed.


Related Article: A Great Year for Midwestern Innovation

ENR Subscribe

Related Articles

Best Residential/Hospitality Project: Aurora at North Bethesda

Best Project-Residential/Hospitality: George Mason University

Project of the Year and Best Project Residential/Hospitality: OneEleven

Post a comment to this article

Report Abusive Comment


Top Lists

Top Design Firms See a Decline in RevenuesTop Design Firms
Top Design Firms Build Bridges to the Future

Click to complete ENR Midwest's Regional Top Design Survey

Top Midwest Contractors: No Recovery In SightTop Contractors
Top Contractors Use New Tech to Meet Demand


Click to complete ENR Midwest's Regional Top Contractor Survey


Midwest Builders Face Worsening EconomyTop Specialty Contractors
A $10-Billion Year for Region's Top Specialty Contractors



Industry Jobs

Videos

ENR Proposals and Bids


ENR twitterfeed
Tweets by ENR_MW

ENR

ENR Jan 9, 2016 Cover

Feb 25, 2019

Big Calif.-Ore. dam removals, which triggered the Jan. 25 federal ruling on state clean-water okays, are proceeding to contract.

View More Subscribe
  • Resources
    • advertise
    • contact us
    • about us
    • photo submissions
    • customer service
    • digital edition
    • Survey And Sample
  • Subscription Center
    • Subscribe
    • Website Registration
    • Privacy Policy
    • eNewsletters
    • FAQ
  • Multimedia
    • Videos
    • Slideshows
    • Reader Photos
    • Photo Contest

Copyright ©2019. All Rights Reserved BNP Media.

Design, CMS, Hosting & Web Development :: ePublishing