The Border Fence K Project consisted of six contracts connecting to create 38 mi of primary vehicle and pedestrian barrier fence from downtown El Paso east to the Fabens area. The total contract value was $170 million, with the majority of construction work completed in just four months.
More than 1,100 people and 600 pieces of equipment were mobilized to complete the schedule-driven project.