2025 West Best Projects
Award of Merit, Highway/Bridge: I-5 over SW 26th Ave. Bridge Replacement

I-5 over SW 26th Ave. Bridge Replacement
Portland, Ore.
Award of Merit
Submitted by David Evans and Associates Inc.
Owner Oregon Dept. of Transportation
Lead Design Firm David Evans and Associates Inc.
General Contractor HP Civil Inc.
Geotechnical Engineer Shannon & Wilson Inc.
Stormwater Engineer Casso Consulting Inc.
Traffic Engineer DKS Associates
Prestressed Slab Sliding System Designer SMG Engineers Inc.
Prime Contractor Project Principal HP Civil Inc.
To replace the heavily worn I-5 overcrossing with a delaminated concrete deck at SW 26th Avenue in Southwest Portland, the project team had to navigate challenging site conditions, limited right-of-way, sensitive residential and environmental areas and difficult topography.
Despite the challenges, the project stayed under budget and was completed on time in October 2024. Originally, the team planned a five-stage onsite detour structure costing $19 million with two years of I-5 traffic disruption. Instead, using ODOT’s value engineering process, the team developed an alternative that eliminated the temporary detour.
Crews built deep foundations and abutments beneath the existing bridge, then slid in precast superstructure slabs while traffic continued overhead. The remaining space was backfilled with low-density cellular concrete (LDCC) and retained with mechanically stabilized earth (MSE) walls.
Once the buried structure was complete, the existing bridge was removed and replaced with full-depth asphalt pavement during a single 56-hour weekend closure. Micropiles were selected to ensure structural integrity without compromising safety or serviceability during construction.
-(10).webp?height=200&t=1666634866&width=200)

