2025 West Best Projects
Best Small Project: California Firefighter Memorial Expansion

California Firefighter Memorial Expansion
Sacramento
BEST PROJECT
Submitted by Turner Construction Co.
Owner California Fire Foundation
Lead Design Firm Romo Studios LLC
General Contractor Turner Construction Co.
Civil Engineer Cunningham Engineering
Structural Engineer Lionakis
MEP Engineer The Engineering Enterprise
Electrical Contractor Royal Electric
Concrete Trademark Concrete Systems Inc.
First unveiled in 2002, this memorial in Sacramento’s Capitol Park honors firefighters who have lost their lives in the line of duty since California became a state. The focal point of the memorial is the limestone wall that immortalizes the names of these firefighters. But in 2023, the wall reached capacity and an expansion was needed to ensure the ability to honor future fallen firefighters for the next 100-plus years.
A $6.4-million expansion effort added approximately 15,000 sq ft and integrates new design elements while maintaining harmony with the existing site and the historical significance of the grounds. Key features include new limestone wedge walls for 3,000 additional names, bronze relief panels depicting critical moments in firefighting history, improved accessibility for all visitors and a new bronze sculpture called “Fire’s Out.” Limestone was sourced from the original quarry for a seamless match, while the precut granite, custom bronze inlays and integrated lighting all demanded a 1/16-in. placement tolerance. Multiple surveys, drone imagery and CAD modeling guided every installation, eliminating guesswork and rework.
Photo by Tim Maloney, Technical Imagery Studio
Faced with an immovable deadline of October 2024 for the Annual California Firefighters Memorial Ceremony, the team used proactive strategies such as pull planning, expedited submittals and RFIs, and carefully sequenced construction activities. Early trade partner engagement helped fast-track procurement of long-lead items, such as granite and bronze.
The project’s design-build model also enabled real-time decisions and adaptive creativity on site. The “Hold the Line” statue was finalized during installation, for example, to ensure its visual and emotional impact. Technical issues, including the integration of precut granite with concrete walls and ambiguity in statue positioning were resolved using mock-ups and field surveys.
Crews placed a custom white concrete mix across more than 10,000 sq ft of flatwork and vertical elements. The team delivered the project for $6.4 million—$900,000 under budget—through value engineering, transparent cost tracking and early design decisions.


