2025 Texas & Southeast Best Projects
Best Cultural/Worship: Union Pacific Bush 4141 Locomotive and Marine One Helicopter Pavilion

Union Pacific Bush 4141 Locomotive and Marine One Helicopter Pavilion
College Station, Texas
BEST PROJECT
Submitted by Manhattan Construction Co.
Owner George and Barbara Bush Foundation
Lead Design Firm HKS
General Contractor Manhattan Construction Co.
Structural Engineer Walter P Moore Engineers Inc.
To build a new space that would house two iconic vehicles adjacent to the existing George H.W. Bush Presidential Library, the project team had to design and build a structure around an already displayed historical 268-ton locomotive that couldn’t be moved or touched.
A bit of reverse engineering was the answer, along with multiple feats of sequencing and coordination. Crews built the structure around the train, treating the locomotive as both centerpiece and constraint, anchoring it into the project’s BIM model using precise 3D laser scanning.
Navigating site logistics and the train’s fixed location required just-in-time deliveries with offsite laydown yards and GPS-coordinated crane picks.
Halfway through construction, the owner issued a major change that involved converting a basic catering space into a fully equipped commercial kitchen. The team shifted to reroute utilities, demolish slab and redesign mechanical elements within the nearly finished structure, completing the revision in just two weeks.
Photo by Roy Aguilar
A further challenge was ensuring that the addition would blend in with the existing design of the library.
Here, the pavilion’s exterior limestone veneer was hand-selected to match the original library’s cladding. The team conducted multiple site visits to compare quarry cuts against the original facade in an effort to ensure the pavilion felt like a natural extension.
To ensure clarity across the entire jobsite, the contractor embedded bilingual leads and crew-facing field staff as strategic communicators rather than translators. Every morning walk-through and every job hazard analysis was delivered in both English and in Spanish to make certain that understanding was universal.
Completed under budget and ahead of schedule in September 2024 after two years of construction, the project features multiple sustainable solutions such as electrochromic glass that automatically adjusts to sunlight, recycled steel components, low-VOC interior finishes and a near-zero waste construction approach.


