This website requires certain cookies to work and uses other cookies to help you have the best experience. By visiting this website, certain cookies have already been set, which you may delete and block. By closing this message or continuing to use our site, you agree to the use of cookies. Visit our updated privacy and cookie policy to learn more.
This Website Uses Cookies
By closing this message or continuing to use our site, you agree to our cookie policy. Learn More
This website requires certain cookies to work and uses other cookies to help you have the best experience. By visiting this website, certain cookies have already been set, which you may delete and block. By closing this message or continuing to use our site, you agree to the use of cookies. Visit our updated privacy and cookie policy to learn more.
search
cart
facebook twitter linkedin youtube
  • Sign In
  • Create Account
  • Sign Out
  • My Account
  • News
    • Newswire
  • Features
    • Projects
    • Companies
  • Top Lists
  • Current Issue
  • Blogs
  • Submit Your Photos
    • People
    • Events
    • Projects
  • Resources
    • Proposals & Bids
    • Industry Jobs
    • Subscribe
    • eNewsletter
    • Events
    • Advertise
    • Reprints and Plaques
    • Staff Directory
    • Construction Cities
  • ENR Home
  • Other Regions
    • ENR Home
    • California
    • MidAtlantic
    • Midwest
    • Mountain States
    • New York
    • New England
    • Northwest
    • Southeast
    • Southwest
    • Texas & Louisiana
Home » Viewpoint: Michigan Ditch Tunnel Project Overcomes High-Altitude Contracting Challenges
Mountain States Construction ProjectsMountain States
Tunneling Projects

Viewpoint: Michigan Ditch Tunnel Project Overcomes High-Altitude Contracting Challenges

Michigan Ditch

Crews extract a custom-built tunnel boring machine from Akkerman Inc. in Minnesota. The 96-in.-diameter Akkerman 720 Series II TBM was outfitted with a mixed-face cutterhead that uses 13 disc cutters, 40 scraper teeth and four scraper bars.
Photo courtesy of BT Construction

March 3, 2017
KEYWORDS Michigan Ditch / Tunnel Projects / Underground Construction / Water Projects
Reprints

High in the Never Summer Mountains of Colorado sits a critical piece of infrastructure for the city of Fort Collins Utilities Dept. known as the Michigan Ditch. The 5.2-mile-long ditch was originally constructed in the early 1900s to convey water from the west side of the mountain range to the east. The city purchased the ditch system 40 years ago and has maintained it ever since, placing a $150-million to $300-million value on the collected water it provides.

Although slope instability has plagued the ditch throughout its history, a previously piped section of the ditch through an area known as “the mudslide” moved 21 ft horizontally and 7 ft vertically during the 2014-15 winter. Since the majority of the collected water flows through the landslide area at 100 cu ft per second, the Michigan Ditch was going to be out of service for the foreseeable future and a permanent solution was needed.

Degree of Difficulty

Site logistics at 10,300 ft above sea level make for a challenging and short construction season. The city of Fort Collins used its alternative product delivery system (APDS) in a design-build, team-oriented approach to solve the problem. The program allows the city to quickly move forward on assembling a team.

Picking from a number of pre-qualified and pre-approved designers and contractors in July 2015, the city assembled a design-build team and began discussing options for permanent repairs to the ditch. Ultimately, the construction of a tunnel behind the landslide in competent rock was deemed the best long-term solution.

A thorough geotechnical investigation in late summer 2015 confirmed the tunnel alignment. Crews took eight vertical borings, along with three horizontal borings. The subsurface investigation showed a much-deeper section of the landslide than previously anticipated. Those findings, combined with the geometry of the site, meant that a curved tunnel alignment would work best to keep the ditch in solid bedrock.

Additional considerations on tunneling methods and carrier-pipe selection produced a final plan that called for a 765-ft-long, 8-ft-diameter tunnel built on a 630-ft radius curve. That allowed for installation of a 60-in.-diameter Hobas carrier pipe. An additional 200 ft of open-cut, 60-in. pipe would also be built to tie into the existing ditch.

Key Challenges

The first challenge was to pick a tunneling machine that the team could transport up to the jobsite. The project is located two miles up a single-track dirt road with a small launch and retrieval site on the side of a mountain, so getting a crane there to unload equipment was not an option.

The design-build team talked with multiple suppliers and decided on a custom-built tunnel boring machine (TBM) from Akkerman Inc. in Minnesota. The 96-in.-diameter Akkerman 720 Series II TBM was outfitted with a mixed-face cutterhead that uses 13 disc cutters, 40 scraper teeth and four scraper bars.

The cutterhead was built out to 98 in. to provide enough overcut to make the 630-ft radius curve.

Also, the TBM weighed less than 50,000 lbs, had a relatively small setup and retrieval footprint, and could be fabricated in the six-month timeframe needed to start construction. If the TBM could handle the geology of the tunnel drive, the construction team was relatively confident it could be delivered and retrieved from the site.

The second challenge was building the tunnel accurately and safely. A state-of-the-art guidance system from VMT Technical Measurement Solutions Inc., combined with routine survey checks by two different survey teams, provided the TBM operators and on-site construction inspectors with constant feedback on the position of the tunnel construction.

The tunnel was built within 0.01 in. horizontally and 1 in. vertically of the design. Building the job safely was a large task for the field supervisory team. Every work shift included a morning and afternoon safety briefing with an open discussion of the upcoming tasks and hazards involved in the work. The project was completed with zero-recordable injuries.

Completing the tunnel within the 2016 summer construction window was the goal from the beginning. Typically, the site is accessible from mid-May through mid-October. The as-expected, mixed-face geology encountered during the tunnel construction resulted in slower than anticipated production and higher tooling changes.

The design-build team worked additional night shifts through September and completed the tunnel on September 29, 2016. Installation of the final 60-in. carrier pipe and tie-in to the ditch took place throughout October, and on October 27, 2016, water ran through the Michigan Ditch behind the landslide. A critical piece of infrastructure was back online for the city of Fort Collins.

John Beckos is a project manager with BT Construction Inc. in Henderson, Colo.


Project Team


Owner: City of Fort Collins, Owen Randall, Chief Engineer


Design-Build (APDS) Team: Stantec Consulting (prime engineer), Lithos Engineering (geotechnical and tunnel engineer), BTrenchless (tunnel contractor), Hydro Construction (general contractor)

 

ENR Subscribe

Related Articles

ARTBA Hopes to Certify Thousands for Safety Training

Theories Outrun Reliable Facts in Florida Bridge Collapse


Top Lists

Top Design FirmsTop Design Firms
Regional Design Work Remains Steady Even as Fees Tighten, Uncertainties Rise


Top ContractorsTop Contractors
Regional Contractors See Market Strength Continuing Through 2020


Top Specialty ContractorsTop Specialty Contractors
Subcontractors Can Expect More Growth, Labor Shortages in 2019



Industry Jobs

Videos

ENR Proposals and Bids


ENR twitterfeed
Tweets by ENR_MS

ENR

ENR Digital Edition Cover

Dec 9, 2019

A joint venture of Skanska, Corman Kokosing Construction Co. and McLean Contracting Co. is moving toward an early 2020 construction start for a $463-million replacement for a 79-year-old bridge across the Potomac River, south of Washington, D.C.

View More Create Account
  • Resources
    • advertise
    • contact us
    • about us
    • photo submissions
    • customer service
    • digital edition
    • Survey And Sample
  • Subscription Center
    • Subscribe
    • Website Registration
    • Privacy Policy
    • eNewsletters
    • FAQ
  • Multimedia
    • Videos
    • Slideshows
    • Photo Contest

Copyright ©2019. All Rights Reserved BNP Media.

Design, CMS, Hosting & Web Development :: ePublishing