In its latest report on Everglades restoration, the National Research Council tempered mild praise for "fairly modest progress" in the $13.5-billion plan with its concerns over climate change, rising sea levels and the invasion of non-native plant and animal species.

Photo courtesy South Florida Water Management District
The report highlighted successes, such as the 85-percent completion of the Kissimmee River Restoration project, which undoes a 1960s channelization of the river.

The fifth congressionally mandated biennial report on the Comprehensive Everglades Restoration Plan (CERP), released on June 26 by a 14-member scientific committee, criticizes the financial, procedural and policy constraints that have impeded project implementation. Those constraints include infrequent passage of Water Resources Development Acts by Congress. The committee called for expedited implementation to avert further degradation of the ecosystem.

To people outside Florida, Everglades restoration is an immense money pit advancing at a snail's pace. But the Everglades are also essential to the health of the South Florida economy as well as its ecosystem, being a principal source of public water supply in addition to being an attraction for tourists.

CERP progress flows at the same languid rate as the water through the Glades, but it does flow. The report highlights successes such as raising a mile of the Tamiami Trail to unblock the flow of water into the Glades; near-completion of Picayune Strand restoration due to a failed residential development; ecosystem responses to phased implementation of several projects that restored "sheet flow" into Florida and Biscayne bays; and 85% completion of the Kissimmee River Restoration to undo a disastrous channelization of the river in the 1960s.

But the Everglades program needs updating to integrate climate change into future ongoing analysis and monitoring. Implementation priorities must be revised "to focus resources on those projects with the greatest potential to avert ecosystem degradation and provide long-term benefits considering sea-level rise and potential changes in temperature and precipitation," the report says.


Nearing Completion

Before the 1960s, the Kissimmee River, headwaters of the Everglades, was a 103-mile-long meandering stream feeding into Lake Okeechobee; then, the Corps converted it into the 40-mile-long C-38 canal for flood control. Now, at a cost of $727 million, its restoration is 86% complete. "This is the crown jewel of ecosystem restoration," says Howard Gonzales, ecosystem branch chief for the Corps of Engineers Jacksonville District in Florida. When natural conditions are restored, "ecosystems respond almost immediately," he says. Five projects remain to be awarded, and they are "relatively small—backfilling and structures to keep backfill in place," he says. Completion is scheduled for 2019.

Built in the 1920s, the Tamiami Trail, part of U.S. Route 41, effectively dammed the flow of water into the Everglades, devastating its ecology. In December 2013, an $81-million, mile-long section was completed, elevating the road to allow water to flow freely. In August 2013, the state of Florida committed $90 million for its half of the cost to elevate an additional 2.6-mile segment of the highway.

Elevating the Tamiami Trail is part of the Modified Waters Delivery program to restore the broad, shallow flow of water, or sheet flow, that created the Everglades and is needed to maintain the Everglades National Park's health. The $323.2-million C-111 South Dade Project also serves Mod Waters by creating a seepage barrier that helps keep the additional water in Everglades National Park. With three pump stations and a detention area, it is now about 75% complete.

The $620-million Picayune Strand project was the first CERP project to be constructed. The project is converting back into its natural state 55,000 acres of a failed development. Canals have been plugged and roads removed; spreader canals with three pump stations are now being constructed. Two pump stations are scheduled for completion by this fall and the last by fall 2017.

Ecosystem benefits are beginning to appear. "We have seen some changes in salinity levels and in aquatic vegetation," says Eric Draper, Audubon of Florida's executive director. "The marshes seem to be a bit healthier, and Picayune Strand is showing very impressive signs of transition to what the original was like." In the Kissimmee River basin, observed changes include expanded wetlands with swelling populations of largemouth bass and sunfish and a robust, growing diversity of birds, says USACE's Gonzales.

Cost escalation is inevitable in a program as huge, long-running and complex as CERP. When authorized in WRDA 2000, its estimated cost was $7.8 billion; it is now $13.5 billion. While much of that is for purchasing land, there is a large allotment for professional-services fees, says Blake Guillory, executive director of the South Florida Water Management District, the state agency responsible for CERP. "We could have a dozen big projects in the next few years," he says. Thirteen teams comprising 105 separate member firms are on board for design work worth some $90 million in fees, he notes.