Rank | Project/ Location | Project Cost ($ Mil.) | Start Date/ End Date |
Owner | Team |
---|---|---|---|---|---|
1 | VINEYARD WIND 1 ENERGY DEVELOPMENT - 800MV Barnstable, Mass. |
2,800 | Nov. 2021 July 2023 |
Avangrid Renewables/Copenhagen Infrastructure Partners JV |
GC: JDR Cable Systems Ltd./Lawrence Lynch Corp./Linxon |
2 | AMAZON NORTH ANDOVER FULFILLMENT CENTER North Andover, Mass. |
466 | May 2021 Aug. 2022 |
Hillwood Investment Properties |
GC: Whiting-Turner Contracting Design: MacGregor Associates Architects Inc. |
3 | COMBINED SEWER OVERFLOW (CSO) PHASE III DESIGN-BUILD Pawtucket, R.I. |
453 | Aug. 2021 July 2026 |
Narragansett Bay Commission |
GC: CB3A, a JV of CBNA and Barletta Heavy Division Design: AECOM and Stantec |
4 | LOWELL HIGH SCHOOL Lowell, Mass. |
344 | March 2021 July 2026 |
City of Lowell | CM: Suffolk Design: Perkins Eastman |
5 | UMASS CHAN MEDICAL SCHOOL EDUCATION AND RESEARCH BUILDING Worcester, Mass. |
325 | May 2021 Fall 2023 |
University of Massachusetts Building Authority | CM: Shawmut Design & Construction Co. Design: ARC/Architectural Resources Cambridge and ZGF |