This website requires certain cookies to work and uses other cookies to help you have the best experience. By visiting this website, certain cookies have already been set, which you may delete and block. By closing this message or continuing to use our site, you agree to the use of cookies. Visit our updated privacy and cookie policy to learn more.
This Website Uses Cookies By closing this message or continuing to use our site, you agree to our cookie policy. Learn MoreThis website requires certain cookies to work and uses other cookies to help you have the best experience. By visiting this website, certain cookies have already been set, which you may delete and block. By closing this message or continuing to use our site, you agree to the use of cookies. Visit our updated privacy and cookie policy to learn more.
Home » Kiewit's Quick-Fix Scheme Swaps Out Nashville Spans
Kiewit Infrastructure Group beat the clock for a second time, as it demolished and replaced an Interstate 40 bridge in Nashville in less than 58 hours, using accelerated bridge construction to minimize traffic impact in a heavily traveled area.
The Tennessee Dept. of Transportation’s Fast Fix 8 project calls for demolishing and replacing eight pairs of spans on I-40 near the downtown area, closing the highway to all traffic for a total of 13 weekends, so work crews can have full, round-the-clock access to the worksite.