Edmonton city officials are overseeing a review by a structural consultant on what caused four deep steel girders on a new bridge being built over a busy thoroughfare to buckle soon after their placement March 16.
The structure has been stabilized but the project delays are costly, at more than $300,000, and could grow much worse.