Award of Merit Highway/Bridge: NYSTA Cashless Tolling - Design and Construction Quality Assurance
Teamwork, communication and coordination were imperative to safely complete work at 60 construction sites along the 450-mile New York State Thruway within a 14-month construction window. The project spanned toll plaza demolition, roadway and alignment improvements and installation of new electronic toll-collection technology, structures and support infrastructure.
Collaboration between the design-build team and quality assurance staff enabled open-road tolling installation at each site within a 30-day window, followed by a 30-day full system test period. The QA team developed a plan along with the design-builder’s quality control program to efficiently and effectively deliver oversight services in a range of technical disciplines. Collaborative technology tools wirelessly integrated multiple state engineering and field offices, while informal “over the shoulder” reviews allowed formal design submission review with few, if any, comments.