Material shortages presented challenges throughout construction of the 190,000-sq-ft data center. The largest impact was due to a shortage of resin for the roofing insulation. One hundred and fourteen trucks of insulation were required to re-pitch the existing deck slope. Initially, five trucks of insulation were planned for delivery each day over a period of one month. Due to shortages, deliveries were severely limited. Turner was able to accurately forecast and improve delivery of material to meet project schedule.
Exterior project scope consisted of saw-cutting and removal of concrete in the mechanical yard area for installation of new utilities; cutting and capping the existing main water lines for installation of a new main water line; and installation of new storm sewer lines and new roof drains. The interior scope included removal of all existing equipment on the roof as well as removal of existing interior equipment and materials.