Completed in August 2021 on-time and on budget at a cost of $45 million, the 238-room, eight-story hotel is just blocks from the Phoenix Convention Center; near Chase Field; Talking Stick Resort Arena, home court of the Phoenix Suns professional basketball team; and shopping, restaurants and cultural amenities such as the landmark Orpheum Theater.
On the street level of the 111,074 sq-ft design-build project is the 1,200-sq-ft Adams Table Patio & Bar; a market; the lobby with a bar and outdoor patio; 6,000-plus sq ft of event space; and a 3,000-sq-ft ballroom. To give the owner an idea of room design, the contractor mocked up a full-size guest room including interior finishes and furniture. This created early alignment between the designer, builder, developer and the brand and helped ensure on-time delivery.