Phillips & Jordan Inc. of Robbinsville, N.C., won the contract Feb. 20 and started immediately to replace the 200-ft section of US 441 in the Great Smoky Mountains National Park that was wiped out by a landslide.
First comes an access road to the bottom of the site and removing 27,000 cu yds of excavation, then filling the football-field-size slide area with 40,000 cu yds of crushed stone that will be “sandwiched” in 1.5-ft layers between layers of geogrid, said Dudley Orr, vice president of Phillips & Jordan.