As a first-of-its-kind, multi-use facility, the three-story, 115,000-sq-ft building provides a singular space for the university’s veteran- and military-focused programs and organizations to work, learn, gather and celebrate.
Though the structure appears as a natural complement to its surroundings, the constraints of multiple adjacent campus buildings made early engagement with trade partners a must to optimize project phasing and procurement. Pull-planning at the shop drawing stage determined the exact sequence for each trade to work on site and for material logistics. With extremely limited onsite storage, deliveries and concrete were scheduled to be completed before the morning rush hour.