Crews are focusing on punch-list items and fiber-reinforced wrapping of bridge columns following a fast-track overpass replacement made possible by long-standing relationships between subcontractors and suppliers and a contracting company’s history of similar feats, according to project team members.
Myers & Sons Construction, the successor company to C.C. Myers, earned an $8-million early-completion bonus in May for replacing an 800-ft-long dual-deck overpass at Highway 101 and Alemany Boulevard in San Francisco. The scheduled 10-day job, completed in eight, had originally been planned for July.