At 9:30 p.m. on Friday, June 28, at a rate of approximately 1,000 cu yds per hour, 140 workers from the Conco Cos. began the job, which required 1,348 truck trips to six batch plants, for the mat, which contains 13,478 cu yd of concrete. The mat will support a 39-story tower.