Of the $1.3 billion in American Recovery and Reinvestment Act funds scheduled for delivery to Amtrak projects, almost $50 million will go to California projects – half for a new LA Maintenance Facility and most of the balance to meet accessibility requirements.
The maintenance facility is planned as a pre-engineered metal building 820 ft long by 70 ft wide, semi-enclosed with a pit running the length of the building. It will include equipment to remove, clean and service train cars. The project will go to bid in October with construction starting in January, 2010. It could take 12 to 16 months to complete.