This website requires certain cookies to work and uses other cookies to help you have the best experience. By visiting this website, certain cookies have already been set, which you may delete and block. By closing this message or continuing to use our site, you agree to the use of cookies. Visit our updated privacy and cookie policy to learn more.
This Website Uses Cookies By closing this message or continuing to use our site, you agree to our cookie policy. Learn MoreThis website requires certain cookies to work and uses other cookies to help you have the best experience. By visiting this website, certain cookies have already been set, which you may delete and block. By closing this message or continuing to use our site, you agree to the use of cookies. Visit our updated privacy and cookie policy to learn more.
Home » More Troubles, Less Support for Energy Dept.'s MOX Project
The Dept. of Energy's $7.7-billion Mixed Oxide Fuel Fabrication Facility at the Savannah River Site in Aiken, S.C., isn't dead yet. But the Obama administration's March budget request to put the unfinished plutonium disposal facility into "cold standby" could sound the troubled project's death knell.
The lack of an official cost and schedule estimate, lax oversight by the project owner and suspected unforeseen design challenges sent construction costs soaring, according to a recent report from the Government Accountability Office (GAO). Long-term operational costs have more than doubled over early estimates, and DOE has failed to line up a utility willing to use MOX fuel. For an administration under pressure to rein in federal spending, the decision to seek other alternatives for disposing of the material was a relatively easy call.