The St. Luke’s Sugar Land Hospital team faced a potentially project-ending problem soon after construction of the new facility began, but it pulled together to keep the job on track.
The initial construction budget outlined the use of a spread-footing foundation for the five-story, 335,000-sq-ft hospital and medical office building, a method that is typically cheaper than piers. However, a detailed evaluation showed that this type of foundation would not work.