The arrival of Hurricane Ike during construction of the five-building corporate administrative campus resulted in a six-week disruption in permanent power to the jobsite.
The loss of power delayed material delivery and postponed the start of interior construction, which requires conditioned air to prevent mold in drywall and damage to millwork from moisture in the air.