Clark/McCarthy, A Joint Venture, recently finished the $575-million, LEED-silver-certified Tom Bradley International Terminal Improvements and Baggage Screening Systems Project at Los Angeles International Airport.
Over two-and-a-half years, the Clark/McCarthy team completed 1 million sq ft of renovation work and upgrades. The project team replaced TBIT�s outdated baggage handling system with an in-line system, completely overhauled its existing mechanical, electrical, plumbing and information technology systems, and built a new gate to accommodate the 800-passenger Airbus A380 aircraft.