ILLINOIS JRM Technology LLC is planning to build a six-story, 315,000-sq-ft data center at 111 E. Cermak Rd. in Chicago. James McHugh Construction Co. has been chosen as the design-build contractor, with ESD Inc. as lead architect/engineer. The building will be reinforced concrete, with 18-ft ceilings, heavy floor loading, space for full generator backups and heavy-duty, high-efficiency cooling systems. It will aim to achieve LEED-certified Gold and will include a green roof and fresh air cooling. Construction is expected to begin during fall 2010 and be completed by late 2011. James McHugh Construction Co., 1737 S. Michigan Ave., Chicago, 60616.
KENTUCKY The U.S. Army Corps of Engineers has awarded ACC Construction Co. Inc. a $20.8-million firm-fixed-price design-build contract for a special operations facility battalion complex, Phase 4, at Fort Campbell. The project is expected to be completed by June 2012. ACC Construction Company, Inc., 635 N.W. Frontage Rd., Augusta, Ga. 30907.