The $35.7-million project will also include raising electrical equipment up to the 500-year flood level.
The Bay Park Sewage Treatment Plant in Nassau County, N.Y., is set to begin work in May on a $35.7-million project to build three electrical unit substations. The design-bid-build project, headed by the joint venture team of Hazen & Sawyer and Arcadis U.S., is targeting completion in March 2016, says Eric Mills, senior associate at Hazen & Sawyer.