UNIQUE
Combo of strand jacks, trestles and skids set orthotropic
deck sections. (Photo courtesy of FCI )
Marking a milestone
for the first suspension bridge to be built in 30 years in the
U.S., a contractor has successfully completed what project officials
call an unprecedented combination of schemes to lift, swing
and roll 24 orthotropic deck sections into place. Officials
say that the unusual combination of strand jacks, trestles,
skids, and other equipment will offer about $1 million in cost
savings and flexibility on the $217-million Alfred Zampa Memorial
Bridge north of San Francisco.
Completion of 83 days of work last
month by the joint venture team of FCI Constructors Inc. and
Cleveland Bridge California Inc. kicked off the final phase
of construction for the 2,390-ft-long bridge, which will span
the Carquinez Straits on Interstate 80 between Crockett and
Vallejo. The project is on track for an October opening, says
Curtis Weltz, project manager for FCI/Cleveland Bridge.
The use of strand jacks in bridge
construction has been done before, says Brian Boal, a senior
bridge engineer for the California Dept. of Transportation.
"But not 600-ton complete orthotropic deck units swinging
up onto suspension bridges," he says. The orthotropic
deck is the first in the U.S. (ENR 12/24/01 p. 12).
The bridges location next
to a 76-year-old cantilevered steel truss bridge slated for
demolition made use of a gantry mounted on the main cable
impractical, says Mark Allison, project engineer for FCI/Cleveland
Bridge. "Normal lifting schemes could not be used, and
therefore we had to come with hybrid lifting schemes,"
Allison says, because the old and new bridges are located
only 40 ft apart at the northern anchorage and 60 ft in mid-channel.
For efficiency, the contractors
decided to erect the 95-ft-wide deck in 24 sections rather
than 48 as originally specified. Cutting the number of sections
in half will minimize deck welding and save about $1 million,
says Weltz.
The decision to use larger sections,
which range from 79 to 163 ft in length and 520 to 800 metric
tons in weight, required extensive followup design analysis,
says Dyab A. Khazem, lead project engineer in the New York
City office of Parsons Transportation Group. The scheme concentrated
the loads far more than if a gantry had been used, Khazem
says, doubling stresses on the temporary clamps to over 2,000
kilonewtons, for example.
Strand jacks with a 290-metric-ton
capacity proved to be key. Four jacks were mounted on each
deck section and attached to temporary strands suspended from
the main cable. To maintain a 12-in. tolerance as each unit
was raised, tugboats stabilized the ships carrying the deck,
Allison says.
For direct vertical lifts, which
constituted about half of the total, the sections were raised
about 100 ft to their final positions, where they were connected
to permanent suspenders. Once a section was in place, the
jack assembly, generator, and other equipment were lowered
onto a ship below so it could be loaded onto the next section.
NEW
Bay Area crossing is first U.S. suspension bridge built
in years.
(Photo courtesy of FCI )
Other lifts proved more complex.
Two sections closest to the northern anchorage were too far
inland to be reached directly by ship. Instead, each section
had to be unloaded from a barge and raised 150 ft onto the
embankment, where it was placed onto a 300-ft-long reinforced
concrete pad equipped with rollers. Moving these segments
into position took up to 10 days, says Allison.
Near the south tower, deck sections
were lifted onto specially constructed skids on top of a 600-ft-long
trestle. Each section was mounted on walking jacks and strands
were attached at 45° angles. The unit moved forward until
the angled cables gradually became vertical. The process was
repeated until the section reached its final position, Allison
says.