The Tennessee Valley Authority is taking over the management of the construction of the second unit at the Watts Bar nuclear plant after the construction schedule slipped under the current contractor, the federal power producer said Wednesday.
TVA renegotiated its engineering, procurement and construction contract with Bechtel Power, Terry Johnson, a TVA spokesman, said. TVA will take over as project manager while Bechtel retains the technical portion of the contract, he said.