In an otherwise troubled time for new coal-fired projects, the Mississippi Public Service Commission has approved Gulfport, Miss.-based Mississippi Power�s plans to build a new 582-MW integrated gasification/combined-cycle plant in Kemper County�but with a $2.88-billion cost cap.
Mississippi Power plans to complete the Kemper project as soon as 2014, said utility spokeswoman Cindy Duvall. The prime construction contractor will be selected soon, with project construction to be managed by Southern Co. Engineering and Construction Services. A sister company, Southern Co. Services, will handle primary design, Duvall says. Kemper�s �gasification island� is being designed by KBR, Houston.