After analyzing the performance of 975 light and heavy industrial projects in its benchmarking database, the Construction Industry Institute found that only 5.4% met "best in class" predictability in terms of cost and schedule. While it is no surprise that over-budget and behind-schedule jobs pose problems for owners, the report also concludes that projects under budget and ahead of schedule create a missed opportunity for owners because money set aside for such projects cannot be invested in other ways.